Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page.
*This report is submitted from ICS on a weekly basis.
Richfield High School
Completed week ending Friday, June 11, 2021
- Continued commissioning of chiller/cooling system took place
Planned week ending Friday, June 18, 2021
- Continue commissioning
Centennial Elementary
Completed week ending Friday, June 11, 2021
- Contractors addressed issues identified on the IEA Commissioning Log
Planned week ending Friday, June 18, 2021
- Contractors to continue to address items identified on the IEA Commissioning Log
Sheridan Hills Elementary
Completed week ending Friday, June 11, 2021
- District staff and All Furniture completed the move-out of the Kitchen, Cafeteria, and the remaining classrooms to be renovated
- Contractor began demolition in the Kitchen
- Contractor began demolition of existing exterior walls required for the installation of the new structural steel at the Kitchen/Receiving addition
Planned week ending Friday, June 18, 2021
- Contractor to continue demolition of existing exterior walls required for the installation of the new structural steel at the Kitchen/Receiving addition
- Begin setting structural steel at the Kitchen/Receiving area addition
- Continue demolition in the Kitchen/Cafeteria
- Continue selective demolition in the classroom wings
- Owner’s abatement contractor to re-mobilize and continue their removals
Richfield Middle School
Completed week ending Friday, June 11, 2021
- Finished up punch list items in administration space
- Finished boiler removal and started boiler room concrete floor removal
- Put floor protection down for main entrance work
- Started demolition for dishwasher room
- Issued drawings for pricing of the new Best Buy Teen Tech Center
Planned week ending Friday, June 18, 2021
- Finish boiler room concrete floor removal
- Underground piping in boiler room
- Demolition at main entrance and bathrooms near loading dock
- Removal of concrete floors in kitchen
- Removal of flooring in cafeteria
Richfield STEM Elementary
Completed week ending Friday, June 11, 2021
- Test, balance, and commission chiller
Planned week ending Friday, June 18, 2021
- Test, balance and commission chiller
Central Education Center
Completed week ending Friday, June 11, 2021
- Contractor worked to address items noted on the above ceiling punch list the Admin area and Area D offices
- New air handling units were delivered and set in the building
- Owner’s abatement contractor completed the removal of the underground fuel storage tank
- District staff and All Furniture completed the move out of the classroom wings
- Completed casework installation in the Admin space and Area D offices
- Began selective demolition in the classroom wings
Planned week ending Friday, June 18, 2021
- Complete acoustical ceiling tile installation in the Admin space and Area D offices
- Complete doors and hardware installation in the Admin space and Area D offices
- Continue selective demolition in the classroom wings
- Begin site demo and earthwork at the chiller enclosure expansion
- Owner’s abatement contractor to remobilize and continue their removals