ICS Weekly Report: February 12, 2021

Sheridan Hills Elementary students learn during a field trip to Wood Lake Nature Center

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, February 12, 2021

  • Continued punch list items (terrazzo floor patching)
  • Continued testing, balancing, and commissioning

Planned week ending Friday, February 19, 2021

  • Continue punch list items
  • Continue testing, balancing, and commissioning

Centennial Elementary

Completed week ending Friday, February 12, 2021

  • IEA Commissioning to continue commissioning the mechanical/HVAC systems
  • Contractors continued working IEA Commissioning log items

Planned week ending Friday, February 19, 2021

  • Contractors to continue working to address IEA Commissioning log items
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems

Sheridan Hills Elementary

Completed week ending Friday, February 12, 2021

  • IEA Commissioning continued the commissioning of the mechanical/HVAC systems
  • Contractors continued working to address punch list and IEA Commissioning log items

Planned week ending Friday, February 19, 2021

  • IEA Commissioning to continue commissioning the mechanical/HVAC systems
  • Contractors continue to address punch list and IEA Commissioning log items

Richfield Middle School

Completed week ending Friday, February 12, 2021

  • Third Floor Restrooms
    • Punch list was identified
  • Second Floor Restrooms
    • Finished installing ceilings
    • Punch list was identified
  • First Floor Restrooms
    • Continued mechanical and electrical rough ins
    • Continued wall framing
    • Sheet rocked south bathrooms
  • Existing Administration Offices/New Special Education Suite
    • Continued painting
    • Continued ceiling grid
  • Existing Music Suite/New Design Lab
    • Remove wall for lab opening
    • Wall framing
    • Continued mechanical and electrical rough ins
    • Finished ceiling in band room
    • Reinstalled band room storage cabinets
  • Wood Shop/New Administration/Fab Lab
    • Mechanical rough ins
    • Wall framing
    • Set corridor doors

Planned week ending Friday, February 19, 2021

  • Third Floor Restrooms
    • Punch list
  • Second Floor Restrooms
    • Punch list
    • Final cleaning
  • First Floor Restrooms
    • Sheet rock north bathrooms
    • Start tiling in south bathrooms
    • Install ceiling grid
  • Existing Administration Offices/New Special Education Suite
    • Continue painting
    • Continue ceiling grid
  • Existing Music Suite/New Design Lab
    • Wall framing
    • Continue mechanical and electrical rough ins
    • Infill choir room tiered floor with insulation
  • Wood Shop/New Administration/Fab Lab
    • Mechanical rough ins
    • Continue wall framing

Richfield STEM Elementary

Completed week ending Friday, February 12, 2021

  • Stairwell soffit repairs
  • Continued commissioning

Planned week ending Friday, February 19, 2021

  • Continue commissioning

Richfield Dual Language School

Completed week ending Friday, February 12, 2021

  • ICS Commissioning was on-site to review open commissioning list items for completion
  • Contractors continued working to address items noted on the commissioning corrective action log

Planned week ending Friday, February 19, 2021

  • Contractors to continue working to address items noted on the commissioning corrective action log

Central Education Center

Completed week ending Friday, February 12, 2021

  • Material submittals are being uploaded to Procore for review and approval
  • ICS and Central Ed. staff met on-site with District IT to coordinate the required IT support for the upcoming renovation
  • ICS and Rochon completed a revised temporary partition plan that was reviewed and accepted by the City Building Official
  • Conducted the first weekly Construction Progress/Coordination meeting
  • ICS, IEA and Rochon met on-site to coordinate abatement activities for the week of Feb. 22

Planned week ending Friday, February 19, 2021

  • District IT to begin facilitating moving staff technology items out of the construction areas
  • All Furniture (moving coming) to complete the move-out of district items out of the Phase 1 construction area
  • Continue with weekly Construction Progress/Coordination meetings
  • Continue receiving and reviewing material submittals