Maintenance/Transportation Building

Completed month of February 2022

  • Continued collecting, reviewing, and processing submittals.
  • Responded to contractor RFIs.
  • Confirmed design with district IT.

Planned for month of March 2022

  • Follow up and ensure permits are secured.
  • Facilitate contractor mobilization.
  • Complete abatement in men’s bathroom.
  • Conduct Demo.
  • Begin plumbing rough-in.

Sheridan Hills Elementary

Completed month of February 2022

  • Final Special Testing and Inspection Report, Commissioning Report sent to the City for review and acceptance.
  • ICS and Wold continued reviewing punch list items for final acceptance.
  • Installed metal panels on the trash enclosure gates.

Planned for month of March 2022

  • Contractors to complete all remaining open punch list items, 3 items remain.
  • ICS and Wold to continue reviewing punch list items for final acceptance.

Richfield Middle School

Completed month of February 2022

  • Continued punch list, commissioning, testing, and balancing
  • Received all close out documentation, operations and maintenance manuals, warranty, and as-built drawings

Planned for month of March 2022

  • Continue punch list, commissioning, testing, and balancing
  • Release retainage
  • Execute final change order and last pay application
  • Deliver portions of furniture for the Best Buy Teen Tech Center

Central Education Center

Completed month of February 2022

  • Contractor addressed punch list items.
  • Compiled electrical operation and maintenance manuals and as-built drawings.
  • Contractor addressed commissioning items.
  • Received and compiled warranty documentation.

Planned for month of March 2022

  • Obtain and review mechanical operation and maintenance manuals, warranty information, and as-built drawings.
  • ICS Commissioning to confirm documented issues have been addressed.
  • ICS Commissioning to conduct sequence testing on HVAC system.
  • Commissioning of chiller and dual temp system to be completed in spring.
  • Install operable walls and train personnel.

Download the PDF Report

Read More

Christina Gonzalez

Director of Student Support Services, Christina Gonzalez, has been awarded the Park Nicollet Foundation 2022 Community Service Award for her leadership, dedication and commitment to supporting students and families.

Quick Update

Are you new to RPS? Join us for a school tour of Sheridan Hills! Learn more and register now.